E.ON: Offshore wind project Rampion starts power generation

Tuesday, 28 November 2017 12:09

The offshore wind farm Rampion in the English Channel has started generating electricity. According to E.ON, the first turbine was commissioned. 115 additional turbines will be connected to the grid in stages over the next few months. The offshore work for the Rampion project began in autumn 2015 with the preparation of the seabed for the turbine foundations. The first monopile was installed at the beginning of 2016. The installation of the turbines began in March 2017 and was...Request free trial