A co-ordinated £61.4m package of essential maintenance and
improvement work is underway on motorways and major A-roads across
the East of England. The work – the bulk of which starts this
month – includes resurfacing, safety barrier and lighting upgrades,
drainage maintenance and repairs and new signs and road markings on
many of the region’s busiest roads. In particular, it includes:
£3.4m for new noise reducing barriers at eight locations along the
M40 in...Request free trial
A co-ordinated £61.4m package of essential maintenance
and improvement work is underway on motorways and major A-roads
across the East of England.
The work – the bulk of which starts this month – includes
resurfacing, safety barrier and lighting upgrades, drainage
maintenance and repairs and new signs and road markings on many
of the region’s busiest roads. In particular, it includes:
- £3.4m for new noise reducing barriers at eight locations
along the M40 in Buckingham and South Oxfordshire
- £3.1m for safety upgrades at the Hare Green Roundabout,
Harwich Road junction on the A120 near Colchester
- £3.5m for major repairs to accident damaged bridges on the
A47 Saddlebow interchange at King’s Lynn
- £1.9m for resurfacing on the A1 between Langford and Baldock
- £1.1m to repair a bridge on the A14 at Claydon
- £3.2m for resurfacing on the A11 between Besthorpe and
Spooner Row
The work, which is all being carried out between now and next
summer, is part of Highways England’s commitment to improve
safety and ensure better journeys across the East region’s
busiest roads. It will be carried out in phases across different
roads to minimise its impact on people’s journeys.
Highways England regional Capital Delivery Team Leader Aran
Nugent said:
This work will improve safety and provide smoother journeys for
the millions of drivers that use our road network across the
East of England every day.
We care about drivers’ journeys and we understand that
roadworks can cause some disruption for drivers and local
residents, so we have planned the work carefully and closely
with local authorities, local parishes and other transport
services to reduce its impact as much as we can.
While we are carrying out this essential work, I would urge
motorists to plan their journeys ahead and allow extra time
where needed.
The work has been planned as follows, weather permitting, and
further details on each scheme will be made available in advance
via Traffic England and local media to help people plan ahead:
|
Road*
|
Main activities
|
Expected dates
|
|
A12
|
Resurfacing, road markings, safety improvements, safety
barrier repairs, traffic signals, bridge repairs, safety
improvements
|
November 2017 – March 2018
|
|
A120
|
Slip road improvements, bridge refurbishment, signage
improvements, safety improvements, lighting renewal,
carriageway repairs, resurfacing
|
November 2017 – March 2018
|
|
A47
|
Bridge repairs, safety improvements, road markings, safety
improvements, pedestrian warning signs, traffic signals,
layby resurfacing, weather station renewal
|
Ongoing, completion by March 2018
|
|
M11
|
Resurfacing, drainage works, embankment repairs, barrier
repairs, sign replacement
|
Ongoing, completion by November 2017
|
|
A14 (Suffolk)
|
Weather station relocation, signage improvements, safety
improvements, lighting renewal, bridge repairs, concrete
carriageway repairs, resurfacing
|
Ongoing, completion by March 2018
|
|
A14 (Cambs)
|
Resurfacing, bridge repairs, road markings and fencing
|
October 2017 – March 2018
|
|
A428
|
Signs and road markings safety improvements
|
January 2018
|
|
A1 / A1(M)
|
Signs and road markings, resurfacing, safety improvements,
bridge repairs, weather station upgrade, electrical
repairs, drainage repairs, technology improvements,
upgrading street lighting to LED, vegetation removal,
landscape improvements
|
Ongoing, completion by March 2018
|
|
M1
|
Resurfacing, bridge repairs, road markings, technology
improvements, electrical repairs, upgrading street lighting
to LED
|
November 2017 to March 2018
|
|
A421
|
Signs and road markings, electrical repairs, safety
improvements
|
October 2017
|
|
A5
|
Signs and road markings, weather station upgrade, upgrading
street lighting to LED, traffic signal improvements
|
October 2017 to March 2017
|
|
M40
|
Noise barrier installation at seven sites along the M40;
technology renewal at three locations in Buckinghamshire
|
January 2018 – March 2018
|
*Each activity is at specific locations along the road, not along
the whole road unless otherwise stated.
|