Magnox: Early Contract Terminations 3.41 pm Rebecca
Long Bailey (Salford and Eccles) (Lab) (Urgent Question): To
ask the Secretary of State for Business, Energy and Industrial
Strategy if he will make a statement on the Nuclear Decommissioning
Authority’s early contract terminations at the Magnox estate? The
Secretary of State for Business, Energy and...Request free trial
Magnox: Early Contract Terminations
3.41 pm
-
(Salford and
Eccles) (Lab)
(Urgent Question): To ask the Secretary of State for
Business, Energy and Industrial Strategy if he will make a
statement on the Nuclear Decommissioning Authority’s early
contract terminations at the Magnox estate?
-
The Secretary of State for Business, Energy and Industrial
Strategy (Greg Clark)
This morning, I informed the House that the NDA has
terminated its contract with the Cavendish Fluor
Partnership for the decommissioning of 12 redundant Magnox
sites. The NDA ran a £6.1 billion tender process from April
2012, which resulted in a 14-year contract being awarded in
September 2014 to the partnership, which is a joint venture
between the British firm, Cavendish Nuclear, and Fluor Inc.
CFP started work on the estate on 1 September 2014 and
there then started a consolidation process to ensure that
the scope of the 2012 tender matched the actual status of
decommissioning. It became clear to the NDA that there is a
significant mismatch between the work that was tendered for
and the actual scale of the work that is required to be
carried out. The NDA board concluded that it should
terminate the contract on two years’ notice. Termination is
made with the agreement of CFP and is no reflection
whatsoever on its performance.
Dealing safely with the UK’s nuclear legacy is fundamental
and non-negotiable. Decommissioning work will continue
under CFP for a further two and a half years. The NDA will
establish arrangements for a replacement contracting
structure to be put in place for when the current contract
ends. The NDA has also settled outstanding claims against
it by Energy Solutions and Bechtel in relation to the 2014
Magnox contract. The NDA was found by the High Court to
have wrongly decided the outcome of the procurement
process. It is clear that the 2012 tender process was
deeply flawed. The NDA has agreed settlement payments with
Energy Solutions of £76.5 million, plus £8.5 million of
costs, and with Bechtel of $14.8 million, plus costs of
about £462,000—approximately £12.5 million in total.
Those are very substantial costs, which could have risen
further if the case had proceeded. Taxpayers must be able
to be confident that public bodies are operating
effectively and securing value for money. Where that has
not been achieved, such bodies should be subject to
rigorous scrutiny. I have therefore established an
independent inquiry into the original procurement process
and why the 2014 contract proved unsustainable. Those are
separate issues, but they need to be examined thoroughly. I
have asked Mr Steve Holliday, the former chief executive of
National Grid plc, to lead this inquiry. It will take a
cradle-to-grave approach, beginning with the NDA’s
procurement and ending with the contract termination. The
inquiry will set out the lessons learnt and recommend any
further actions it sees fit, including any disciplinary
investigations or proceedings that may be appropriate. The
inquiry will report jointly to me and to the Cabinet
Secretary, and his report will be available to this House
and to the Select Committee.
This was a defective procurement with significant financial
consequences, and I am determined that the lessons to be
learned should be exposed and understood; that those
responsible should be properly held to account; and that
this should never happen again.
-
The NDA has withdrawn its appeal against the judgment that
was handed down in late July last year, so will the
Secretary of State explain why this decision has been taken
now, why the matter was brought to appeal in the first
instance, and whether both actions were sanctioned by him
or his predecessor?
The judgment confirmed that the NDA had not acted properly
in the tender process, and that it was
“acutely aware that an unsuccessful bidder might challenge
the outcome of the competition.”
The court stated that the NDA had fudged the evaluation to
achieve a particular outcome. More worryingly, the judge
also confirmed that the NDA attempted to get rid of
information that might have been detrimental to its case,
and there was reference to the shredding of notes. Given
the serious nature of the judgment, will the Secretary of
State assure the House that there will be full public
disclosure of the investigations, and a public hearing?
Does he agree that this case has called into question the
future operation of the NDA? Will he explain what
structural changes are necessary, and when? Can he offer
any assurances to Magnox workers?
Finally, the Secretary of State’s written statement
confirms:
“It has become clear to the NDA…that there is a significant
mismatch between the work that was specified in the
contract as tendered in 2012”.
Will he tell the House when he or his predecessor was first
aware of that mismatch and whether it would have been
apparent from the work that had already been carried out by
previous contractors?
-
The hon. Lady is quite right to ask her questions, and I
hope she will agree that the written ministerial statement
I have made today is thorough and comprehensive. I am very
happy to have conversations with her and the Select
Committee over the weeks and months ahead.
The hon. Lady asked some specific questions about the
termination of the contract and the litigation. On the
latter, there was indeed a Court hearing and judgment in
July last year, and there was another one in December on
which the NDA has reflected. On 1 March this year—a few
weeks ago—a new chief executive and chair of the NDA took
office. It seemed to me appropriate that a new set of eyes
should consider these matters and the course of action,
rather than those people who were responsible for and
involved in the procurement exercise looking into it. In
answer to her question, it was a decision for the NDA
board—that is how it is constitutionally established—but
its decision required ratification by me, the Chief
Secretary to the Treasury and the accounting officer in my
Department.
The hon. Lady asked some very important questions about the
conduct of the original procurement process and its
management. That is exactly why we need to have an
independent figure—independent of Government and of the
NDA—to make a report available to the House, to me and to
the Cabinet Secretary, not only so that we can learn the
lessons and ensure that things cannot happen again, but so
that, if there is fault and an error has been made, the
recommendation of disciplinary action can follow.
The hon. Lady rightly asked about the Magnox workforce, for
whom this will be a difficult day. I am happy to confirm to
the House that there is no question about the operational
good performance of the contract; it was a question of the
terms of the letting of the contract. Good progress has
been made, and the workforce employed on the
decommissioning contract will continue as planned. When the
report is made available, lessons will be learned about the
NDA’s structure, as well as any particular procedural
aspects.
-
Mr (Maldon)
(Con)
Will my right hon. Friend join me in paying tribute to the
workforce at Bradwell-on-Sea in my constituency? They are
doing a magnificent job in decommissioning the power
station there. Will he confirm that nothing in his
statement will prevent that work from continuing? Will he
also listen to their concerns about the effect on their
pension entitlements of certain changes that have been made
regarding the cap on exit payments?
-
I join my right hon. Friend in paying tribute to the
workforce. As he will be aware, good progress has been made
in decommissioning the site in Bradwell, with the
underground waste vaults containing intermediate level
waste having been cleared and decontaminated. That is a
reflection of the hard work. There is a separate set of
discussions and consultations going on with regard to the
pension arrangements, which is not related to today’s
announcement.
-
(Rutherglen and
Hamilton West) (SNP)
I thank the Secretary of State for his response and the
shadow Secretary of State for securing this urgent
question. This debacle shows that the UK Government cannot
even manage their current nuclear project, which comes at
great cost to the taxpayer, leaving their case for a
nuclear-energy future more threadbare than ever. When we
take into account the bizarre and illogical decision to
leave Euratom, the trade union Prospect is right to be
concerned and to seek reassurances that uncertainty over
the future of decommissioning will not lead to a
deterioration in standards. What assurance can the
Secretary of State give today?
This should be a wake-up call. The UK Government’s nuclear
obsession will do nothing to lower energy bills and will
only burden the next generation with unprecedented
economic, environmental and security instability and risk.
The Tories should do the responsible thing and scrap their
nuclear obsession in favour of investment and renewable
energy in carbon-capture technology. Scottish Renewables
recently reported that one in six renewable energy jobs in
Scotland will be under threat in the next year. Will the
Government acknowledge that their energy policies need to
be reviewed to allow the Scottish Government to continue
with their competent and ambitious vision of a prosperous
green future? Finally, when can we expect full details of
the timetable of the investigation into this matter?
-
A little humility might be appropriate here, because the
Scottish Government provided oversight of this procurement
as part of the NDA competition programme board. I am sure
that the lessons to be learned from 2012 to 2014 also apply
to the Government in Scotland. I am sure that, whatever the
view on future new nuclear power, the people of Scotland,
as well as those of the whole of the United Kingdom, would
want the existing nuclear power stations to be
decommissioned safely and to have arrangements in place to
ensure that that can be done reliably. On the independent
review, which I hope the hon. Lady welcomes, I have asked
Mr Holliday to give some interim findings by October, so
that they can inform the further decisions about the
re-letting of the contract.
-
Sir (West Dorset)
(Con)
I am sure that my right hon. Friend will pay no attention
whatsoever to the bizarre asseverations of the Scottish
National party spokesman. In asking Steve Holliday, in whom
we have considerable confidence, to do this review, I hope
that my right hon. Friend will seek to bring the review to
a final conclusion reasonably soon after the interim report
in October so that we can get to the bottom of this matter
and ensure that it does not repeat itself in future years.
-
I agree with my right hon. Friend: it is important quickly
to learn the lessons and to apply them. This is very
important work. The work is being carried out to a high
standard, but those lessons must be learned and applied.
-
Mr (Hartlepool) (Lab)
May I thank the Secretary of State for his courtesy call on
this matter this morning and for his subsequent letter? The
Business, Energy and Industrial Strategy Committee will
challenge hard, but work constructively with him and with
Steve Holliday on this important issue. Will he clarify
whether the inquiry will be confined to the procurement
process, which led to this specific contract? Will it
consider other contracts such as the one to decommission
Dounreay, which was awarded to essentially the same
consortium that won the Magnox contract? I think that he
has already confirmed this, but will he say whether the
inquiry will be broad enough to consider whether the
governance and management arrangements of the NDA have
always been, and will continue to be, fit for purpose?
-
I am grateful to the Chairman of the Select Committee for
what he said. I can confirm that the governance and the
management arrangements of the NDA are very much in scope.
I put the terms of reference in the Library of both Houses
of Parliament this morning. It is open to Mr Holliday to go
where the evidence takes him—to use that phrase on this.
The particular concern is over this contract, but if he
feels that he needs to look at other aspects of the NDA’s
management, he is absolutely free to do so.
-
(Charnwood)
(Con)
I welcome the characteristic candour and openness with
which the Secretary of State has approached the issue. Will
he reassure me and the House that the scope of the inquiry
will look not only at the NDA, but—as I think he just
alluded to—at the role, if any, of UK Government
Departments and the Scottish Government in the process?
-
I will, indeed. The terms of reference that were published
with my written statement this morning make it very clear
that, as is absolutely right and proper, the inquiry
applies to the NDA and Government Departments, from the
beginning of the procurement in 2012 to the conclusion of
the litigation and the termination of the contract.
-
(Dwyfor
Meirionnydd) (PC)
Under current plans, Trawsfynydd power station will lose most
of its jobs in less than 10 years. The Government are now in
a position to commit to a programme of continuous
decommissioning, as recommended by the Select Committee on
Welsh Affairs. When will the Secretary of State publish
revised plans following today’s announcement, and will he
agree to meet me to discuss the future of the Trawsfynydd
site?
-
I will certainly meet the hon. Lady. I am glad that she has
given me the opportunity to emphasise that the work will
continue as planned at all the sites. As she will know, work
is ahead of schedule in the plant she mentioned. In the light
of that, I will meet her to update her on the latest timings.
-
(Eddisbury)
(Con)
This was clearly a defective procurement with quite serious
financial consequences. I welcome the Secretary of State’s
determination that the reasons will be exposed, but will he
assure the House that people found to be responsible or at
fault will be brought to account?
-
I can confirm that the terms of reference make it very clear
that the inquiry can make any recommendations that it sees
fit, including as to any disciplinary investigations or
proceedings that may, in its view, be appropriate as a result
of its findings.
-
(Hornsey and Wood Green)
(Lab)
Will the Secretary of State please confirm that the thousands
of people waiting for an outcome on their pensions will not
be ripped off?
-
Yes. There have been constructive discussions with the
representatives of the workforce. Those discussions and
consultations continue. Of course, we want to bring them to a
satisfactory conclusion.
-
(Finchley and Golders Green)
(Con)
The NDA settlement payments are very substantial. Will my
right hon. Friend confirm that although the payments were
made without accepting liability, the cost had the potential
to rise much further were the matter taken to court?
-
My hon. Friend is absolutely right. We have a duty to
consider the further risks to public money, which is why my
accounting officer, the Chief Secretary to the Treasury and I
accepted on advice that, however painful it is—these are
significant sums of money, as my hon. Friend the Member for
Finchley and Golders Green (Mike Freer) said—we should
prevent the sums of money from being even greater.
-
(Wolverhampton South West)
(Lab)
Given the cost problems with the NDA’s Magnox decommissioning
contract, how can the Secretary of State have any confidence
whatever in the cost figures for Hinkley Point C, which will
itself need decommissioning, especially given the farce of
the massive cost overruns and huge time delays in building
the EDF sister reactors in Finland and Normandy, neither of
which has yet opened and each of which is years late?
-
This is about a procurement process that was mis-specified
around decommissioning; it is not against the build costs of
a future reactor. If Steve Holliday’s report includes wider
lessons for the industry, we will be sure to take them.
-
(Bexhill and Battle)
(Con)
All public sector organisations can learn much from
procurement processes and public-private initiatives, as the
£3,700 a minute spent by the NHS on private finance
initiatives would attest. Will the Secretary of State assure
me that all public sector organisations will be given the
opportunity to learn best practice from the Holliday review?
-
I will. It is important when there is such a serious set of
consequences for public money that the conclusions should be
publicly available, and available to this House and to other
Government Departments that may want to reflect on them.
-
Mr (Bury North) (Con)
Will the Secretary of State confirm that the Holliday inquiry
will have reached its final conclusions and issued its final
report in time for any lessons learned to be taken into
account before the new contract process begins?
-
One reason I have asked Mr Holliday to make a report by
October is so that that can happen. I will meet him in the
coming days, as he sets out the scope and timetable, but that
is one of the key reasons for the report, and I am sure he
will want to make his recommendations available for the new
process.
-
Mr (Bolsover)
(Lab)
What were the terms of the pay-off? The Secretary of State
has not mentioned it.
-
I have mentioned the settlement—it is nearly £100 million for
the settlement of the litigation. The chief executive of the
NDA has come to the end of his contract.
|