The National Audit Office has today published its findings from its
investigation into HM Revenue & Customs’ (HMRC) contract with
Concentrix. The three-year contract, signed in May 2014, was to
provide additional capacity and analysis to review and correct
personal tax credit payments. The contract did not work as HMRC
intended and, in November 2016 HMRC and Concentrix agreed to
terminate it and a number of Concentrix staff transferred over to
HMRC.
The investigation looks at the aims and management of the
contract; the decision to terminate it; and the impact of the
contract termination.
The key findings of this investigation are as follows:
- · HMRC
expected its contract with Concentrix to provide good customer
service standards for claimants. It required Concentrix to
follow the same procedures as HMRC when investigating tax credit
claims, after training provided by HMRC. Concentrix collected and
assessed evidence on claimants' circumstances and determined
whether the award was accurate, and made amendments or stopped
awards altogether where it believed the award to be incorrect. It
then made amendments to those claimants' tax credits or stopped
them altogether. HMRC continued to manage awards, recover any
overpayments and deal with claimants' appeals.
- · HMRC
estimated in November 2013 that its contract with Concentrix
would save £1 billion over the life of the contract. HMRC
estimated that Concentrix would provide additional capacity to
investigate up to a further 1.5 million awards per year. Savings
would come from stopping incorrect claims, reducing overpayments,
and the recovery of money already paid out. HMRC expected to pay
Concentrix between £55 million and £75 million over the
three-year life of the contract.
- · In March
2016, HMRC had reduced its forecast of expected savings to £405
million. HMRC analysis identified two main factors that led to
the reduction: a two month delay to the contract start date
because of delays in developing the IT infrastructure to transmit
and manage cases and Concentrix working fewer cases than HMRC
originally expected. Concentrix, however, believes that the
reduced level of savings was as a result of less fraud and error
in the system and changes in the mix of cases it was given to
work.
- · The contract
included incentives for Concentrix to meet customer service and
quality targets. HMRC’s business case recognised the risk of
the supplier increasing profits at the expense of customer
service. To mitigate this risk, HMRC reviewed a sample of cases
each month to measure the quality of compliance decisions by
Concentrix and also required them to meet key performance
indicators for customer service which Concentrix reported its
performance against on a daily, weekly and monthly basis.
- · Between
November 2014 and September 2015 Concentrix consistently failed
to achieve over half of its performance targets, meeting
only 104 of a total 242 applicable monthly performance
indicators. Its performance was worst during the peak renewals
period in mid-2015 when in July it answered an average of 4.8% of
calls within five minutes (target 90%).
- · HMRC reduced
Concentrix's commission payments by a total of £3.5 million over
the life of the contract, after it missed quality and customer
service targets. HMRC paid Concentrix only for the
percentage of cases meeting quality standards and in October
2015, introduced a further penalty that reduced the commission
paid to Concentrix when it failed to meet customer service
targets for handling calls and post.
- · In October
2015, HMRC and Concentrix agreed to vary the
contract, introducing a revision to the performance
management arrangements and an increase in the level of
commission payments. Concentrix's level of
commission increased to 11%, compared with 3.9% (with a
possibility to earn 6.9% if savings reached particular
thresholds) in the initial contract.
- · After some
improvement, the performance of Concentrix fell again during the
2016 renewals process. Concentrix’s failure to process compliance
cases in accordance with its plan meant resourcing in call
centres was not sufficient to meet the resulting increase in
customer calls. Higher than expected terminations where claimants
failed to renew their tax credit awards and IT issues in August
further increased call volumes and delayed processing.
- · By 20
September when the high-risk renewals process was
scheduled to complete, there was a backlog of 181,000 open
cases. Although Concentrix opened 324,000
compliance investigations on high-risk renewal cases, as was
planned, it did not conclude its enquiries and close the cases as
expected. This backlog of cases contributed to the higher than
expected call volumes and award terminations when claimants
failed to renew.
- · Concentrix
was unable to cope with the volume of calls from claimants during
August 2016, which were significantly above forecast. It had
estimated weekly call volumes at around 8,000 during August 2016
but volumes reached six times this level. For example,
in the week commencing 15 August, Concentrix received a peak of
48,000 calls, of which 19,000 were unanswered. Concentrix
redeployed staff to call centres but it was insufficient to cope
with the volume of calls and meet service standards, and was
below the resourcing set out in its plan. This meant that some
claimants were unable to contact Concentrix to discuss their
award.
- · More awards
were terminated as a result of the renewals process than were
expected, increasing demand on the call centre. HMRC stops
making provisional awards to tax credits claimants where they
fail to renew their claim by 31 July. In 2016, the number of
provisional awards terminated as part of the high risk renewals
process conducted by Concentrix was significantly higher than
expected, at 45,000 against 21,800 anticipated in its plan. These
higher than expected terminations would have been lower if
Concentrix had processed more cases prior to 31 July.
Concentrix's performance in August 2016 was also affected by IT
failures. A routine technical update to Concentrix’s systems
on 11 August 2016 prevented its staff from accessing or updating
claimant details for a total period of 26 hours. This lack of
access led to higher call volumes from 12 August onwards. There
is evidence that some claimants had to call multiple times to get
in contact with Concentrix. Concentrix cites two further IT
failures in its and HMRC's systems as contributing factors.
- · HMRC took
steps to mitigate the impact on customers after the problems were
escalated to its senior management on 5 September 2016. HMRC
reallocated a weekly average of 670 (full time equivalent) staff
between 12 September and mid-November 2016 to work on clearing
181,000 cases returned from Concentrix and to answer calls.
- · In November
2016 HMRC and Concentrix agreed to terminate the contract with
immediate effect. In September 2016, HMRC announced that it
would not use the option to extend the contract beyond May 2017.
Following discussions, and consideration of options, HMRC and
Concentrix agreed to terminate the contract.
- · In total,
Concentrix stopped or amended tax credit awards in around 12% of
cases investigated, of which 32% of these decisions were
overturned following a mandatory reconsideration. Concentrix
has stated that the average length of time for which claimants
had their tax credits stopped and then subsequently reinstated
was between six and eight weeks. Between November 2014 and
mid-December 2016, HMRC had paid a total of £86,815 in
compensation for complaints relating to cases handled by
Concentrix.
- · The contract
with Concentrix delivered estimated savings of £193 million
against a payment of £32.5 million.Estimated savings are assessed
as £223 million net of opportunity costs of £30 million relating
to the diversion of HMRC staff to complete Concentrix cases. The
payments to Concentrix included £23.1 million in commission and
£6.9 million that related to mandatory reconsiderations where
decisions were overturned and HMRC agreed as part of termination
not to adjust payments to Concentrix, along with amounts for
partly worked cases and sub-contractor costs following
termination, and additional IT-related costs. HMRC did not meet
any severance costs for staff leaving Concentrix following the
agreement to terminate the contract. Concentrix told us that it
made a loss of £20.5 million on the contract.
- · HMRC will
not replace Concentrix with another third-party provider and
has transferred 243 staff from Concentrix under TUPE regulations
to work on tax credit error and fraud interventions. HMRC
concluded that the risks of a third-party arrangement to customer
service outweighed the benefits, notwithstanding the 'net
positive' savings against costs it reports.
Notes for Editors
- 1. Tax credits are an
annual award (NAO report Figure 2). Because a household's
income is liable to change during the year, the Tax Credits Act
2002 requires HMRC to make a provisional award and calculate
payments based on estimated income. At the end of the tax year,
claimants are required to renew by reporting actual income and
circumstances
2. Error occurs when claimants
do not give HMRC accurate information on their circumstances
before their award is finalised, or provide inaccurate
information that they believe to be correct, or when HMRC makes a
mistake when processing the claim. Fraud occurs when claimants
knowingly give HMRC inaccurate information or deliberately
conceal information to increase the value of their award
- 3. Mandatory
reconsiderations are the process by which claimants can ask to
review a decision on their awards made by HMRC or Concentrix. It
allows the claimant to provide further evidence to assess the
correct award. Claimants can appeal following mandatory
reconsideration. Concentrix handled reconsiderations of its
decision during the contract, HMRC retained responsibility for
handling appeals and complaints
4. TUPE refers to the Transfer
of Undertakings (Protection of Employment) Regulations, which
preserve employees' terms and conditions when a business or
undertaking, or part of one, is transferred to a new employer