The Public Accounts Committee (PAC) has published its report scrutinising mobile
connectivity.
The report finds that the Department for Science, Innovation
& Technology (DSIT) has more work to do to ensure the UK has
the mobile connectivity it needs now and in the future. To meet
its target of increasing 4G coverage to 95% of the UK landmass by
December 2025, progress will need to continue at the same rate as
the past year, even though the remaining locations will be even
harder to reach and connect.
The report warns this pace may not be sustainable, with three of
the four mobile network operators already advising DSIT that they
are each unlikely to meet interim obligations, set by Ofcom, to
increase their own 4G coverage to 88% of the UK landmass by 30
June 2024.
You can also read the attached report here.
You can find out more about the inquiry, including oral and
written evidence, here.
Conclusions and recommendations
-
The Department is not certain what the eventual cost of
the Shared Rural Network programme will be, who will bear cost
increases and how addressing cost increases will impact on
coverage.Cost pressures and delivery challenges
experienced on the programme to date mean that the costs of
delivering masts have been higher than expected. On the
Extended Area Service element of the programme, the
Government's costs have risen by an estimated £44 million due
to irrecoverable VAT and inflation. To absorb these additional
costs, the Department is considering options for delivering the
required increase in 4G coverage but with fewer masts. Cost
pressures also mean that the final cost of the Total Not Spot
element of the programme is uncertain. BDUK considers that it
now has a better understanding of the cost increases on the
Total Not Spot element than it did previously, and under the
agreement by which the Department provides funding for the
Total Not Spot element, it expects that any additional costs
should be funded by the mobile network operators. However,
Ofcom's licence agreements with the operators allow for relief
of their individual obligations if costs are deemed excessive,
creating uncertainty about where any costs will fall or if the
Government's target for 95% 4G coverage will be met.
Recommendation 1: The Department and BDUK should work
closely with the mobile network operators to ensure that
government:
- Gets the information it needs from the operators to gain
certainty on the cost increases; and
- Uses this information to inform decisions on how cost
increases will be managed while at the same time ensuring that
coverage targets are met.
- Fully considers emerging new technologies such as low
orbiting satellites to ensure investments produce the most
cost-effective results.
-
The Department has not identified the specific benefits
it is aiming to achieve in the most remote areas of the UK to
help guide decisions on where investment is most needed to
improve connectivity. To secure good value from
the Shared Rural Network programme, the Department needs to
know where improved connectivity will offer the greatest
benefits for the funding available. However, the Department's
business case for the programme included limited evidence of
the specific benefits of extending mobile coverage into remote
and sparsely populated areas, where building masts may be more
difficult or expensive, or where there may be an impact on the
environment. Stakeholders from the northwest of Scotland, in
areas which are particularly remote, have already raised
concerns about the impact on the environment and questioned
whether the benefits justify the investment of taxpayers'
money. The Department accepts that there is a need for more
information on the benefits of improving connectivity in remote
areas and says that the individual benefits of each mast will
be set out as part of the planning process, which will help to
test the benefits of each site.
Recommendation 2: Now that the proposed locations of
Shared Rural Network masts are more certain, the Department
should revisit its cost benefit analysis to determine more
precisely who will benefit, and how, from its investment in 4G
connectivity. It should use this information to inform final
decisions on mast locations and numbers and to communicate the
case for investment to stakeholders.
-
The Department has not confirmed which specific areas
are in the 5% of the UK landmass that will not have 4G
connectivity, and it does not yet have a plan for ensuring that
consumers and businesses in these areas get the connectivity
they need.At the outset of the programme, the
Department committed to increasing 4G coverage to 95% of the UK
landmass, but, because the location of masts was not certain,
it did not confirm which specific geographical areas would
benefit from better coverage. Although the location of masts
and the areas that will gain 4G coverage is now clearer, the
Department has not set out where the remaining coverage gaps
will be or determined how it will ensure that consumers and
businesses in these areas get the coverage they need. The 5% of
landmass that will not gain coverage from the Shared Rural
Network programme is extremely rural and remote, with very low
population and only small numbers of people travelling through,
and the Department's view is that there is a line to be drawn
on how much to invest in those areas where it might not make
economic sense to build a mast. The Department acknowledges
that it might be more economical to use alternative
technologies such as low earth orbit satellites instead of
masts to provide coverage in these areas.
Recommendation 3: With clearer information about the
proposed location of masts, the Department should now confirm
which areas of the UK will still not have 4G connectivity once
the Shared Rural Network programme is complete. It should assess
the impact of this on communities in these areas and develop a
plan for alternative ways of ensuring they get the connectivity
they need.
-
The mobile coverage reported by Ofcom does not always
reflect the actual level of service that businesses and
consumers experience, and which may sometimes be significantly
worse than reported.The data that Ofcom publishes on
mobile coverage across the UK is based on modelled estimates
provided by the mobile network operators. Ofcom also conducts
sample tests to check the data provided by the mobile network
operators. However, the mobile coverage levels published by
Ofcom do not always reflect the consumer experience. For
example, trees, local geography or different building materials
used within premises can affect the coverage that people
experience. In addition, some people experience worse coverage
inside premises and may only receive a 3G signal indoors,
despite getting a 4G signal outside. The lack of a 4G signal in
some locations may have implications for the connectivity
people will experience when mobile network operators begin
their planned 3G switch off, which they are due to do from this
year and which has already started to happen. The Department
has asked Ofcom to determine how it can improve coverage data
to better reflect people's experiences, and Ofcom is looking at
how it can use crowd-sourced data for this purpose. The
Department has said it will explore with Ofcom the setting up
of a repository so that consumers can report coverage gaps
directly.
Recommendation 4: The Department should take urgent
action to ensure that it has meaningful data on mobile coverage
that reflects people's actual experience. As part of this it
should:
- Work with Ofcom to develop ways that consumers and businesses
can directly report coverage gaps in real-time to help build a
more realistic and detailed picture of mobile coverage across the
UK;
- Ask Ofcom to examine any cases where areas have lost all
mobile connectivity following 3G switch off; and
- Ensure that mechanisms for measuring access to 5G coverage
are fit for purpose.
-
The Department lacks up to date information to track
progress on whether the Shared Rural Network programme will
meet its targets for increasing connectivity on roads and
premises.In addition to the overall target to increase
4G coverage to 95% of the UK landmass, the Department also aims
to provide 280,000 additional premises and 16,000 kilometres of
roads with 4G coverage through the Shared Rural Network
programme. However, the Department is unclear on how many
premises and roads had gained 4G connectivity so far and is
still in discussions with the mobile network operators about
getting the information it needs to track progress against
these targets. Furthermore, it says that Ofcom will not assess
whether the mobile network operators have met these targets
until 2027. Despite not being able to confirm what progress has
been made do far, based on information BDUK has received to
date from the mobile network operators, the Department says it
is confident that it will meet the roads and premises targets.
Recommendation 5: The Department should work with
Ofcom and the mobile network operators to ensure that it can
report publicly on progress against its targets for increasing 4G
connectivity on roads and premises.
-
Progress in improving connectivity on UK railways has
been hampered by a lack of up-to-date coverage
data.Mobile connectivity along major rail routes
remains poor and passengers can often struggle to make calls,
stream videos or work online. Improving rail connectivity is
very challenging, with tunnels, cuttings and safety glass on
modern trains making reception difficult. It is also, according
to the Department, expensive because it requires installation
of infrastructure alongside the railway track. Improving
connectivity on railways is the responsibility of the
Department for Transport and proposals to improve mobile
connectivity need to be judged alongside other priorities for
investment on the railways. However, the data on rail mobile
coverage that is available to inform these investment decisions
is not fit for purpose. There is a lack of granular data
showing, for example, mobile coverage for each metre of rail.
The data is also out of date, with Ofcom publishing its last
study on rail mobile coverage in 2019.
Recommendation 6: Working with Ofcom and the
Department for Transport, the Department should make a plan for
more frequent collection of coverage data on the UK rail network
to help it prioritise the rail lines where improvements in
coverage is most needed. This information should be published on
a regular basis so that rail travellers have clearer information
on the coverage they will experience.
-
The Department's plans for supporting investment in 5G
infrastructure are undeveloped and it has not articulated what
it has achieved from taxpayers' investment to
date.Since 2017, the Department has committed over
£500 million to determine how 5G technology could be used by
consumers and businesses in the UK, to promote investment in
5G, and for research into more advanced technologies. The
Department has published information on the outcomes of its
spending programmes but has not brought information together to
make it clear what it has achieved to date. Nor does the
Department currently plan to directly support the roll-out of
5G infrastructure in the same way as it has done for 4G. There
have been calls for the Government to act quickly to support 5G
deployment in areas where the market is unwilling to deliver,
but the Department is waiting to see how willing the mobile
network operators are to invest and how far the commercial
roll-out progresses before deciding if government investment is
needed. It has set an ambition for standalone 5G to be
available in all populated areas by 2030, but has not yet
defined all populated areas or the level of 5G performance it
considers the UK needs.
Recommendation 7: The Department should set out more
clearly what it has achieved from its investment to date in 5G,
as well as setting more meaningful and measurable targets for
assessing its progress in supporting the roll-out of standalone
5G mobile coverage.