Summary of the
Project
Environmental
Statement
Details
Jackdaw Field Development - BG International Limited -
2021 - D/4260/2021 - Under reviewKey
Dates
- Date Environmental Statement received by the department -
06/05/2021
- Public notice commencement date - 10/05/2021
- Public notice closing date - 09/06/2021
- Further information public notice commencement date -
05/07/2021 & 18/03/2022
- Further information public notice closing date - 05/08/2021
Environmental Statement & associated
documents
- Summary of the Project - Received Date 06/05/2021
- Environmental Statement - Received Date 06/05/2021
- Public Notice - Received Date 10/05/2021
Further Information
- Secretary of State request for provision of further
information - 17/06/2021 & 14/10/2021
- Developer response to Secretary of State request for
provision of further information - Received Date 28/06/2021 &
22/02/2022
- Further information public notice - 05/07/2021 &
16/03/2022
Decision made by the Secretary of State
- Secretary of State notice under regulation 16(1) -
- Secretary of State decision to agree to or refuse to agree to
the OGA granting of consent - Letter to the developer -
05/10/2021
- Secretary of State decision to agree to or refuse to agree to
the OGA granting of consent - 28/09/2021