- Massive rail programme will “literally run out of time” if
key Euston decision delayed further
Following criticism by the Public Accounts Committee over the
lack of transparency from the Department for Transport (DfT) and
HS2 Ltd when the project’s delivery timeline and budget were hit
with serious issues, the Government is now providing the
Committee with “a clearer explanation of costs than we have
previously seen in its reporting to Parliament.”
But the Committee is now “increasingly alarmed” about key
elements of the programme, particularly the lack of progress at
Euston Station, which have the potential to lead to yet more
costs, delays and uncertainty over the promised benefits of the
programme.
The current estimated cost of completing High Speed 2 is between
£72-98 billion (2019 prices), compared to an original budget of
£55.7 billion in 2015 (2015 prices). Civil construction of Phase
One is now planned to finish in 2025, with initial Phase One
services (Old Oak Common to Birmingham Curzon Street) starting
between 2029 and 2033.
Euston station is a key part of Phase One, but despite the
necessary planning consents being in place since last year,
according to HS2 Ltd,the DFT is yet to make key decisions on the
design and approach to construction there. HS2 Ltd told the
Committee it is “getting close to the point where the programme
will literally run out of time” if this next decision is not made
soon.
Government also still needs to decide how Phase 2b – the northern
sections of the route – will integrate with other parts of the
railway and transport system.
The increases in costs have dented public confidence, and the
volume of complaints about disruption and environmental damage
from construction is rising and expected to increase further. The
Committee says HS2 Ltd has an “opportunity to get on the front
foot and engage with communities earlier and more successfully
than it has done so far” - but DfT and HS2 Ltd have been unable
to tell the Committee how they will ensure delivery of the range
of benefits Government has promised to the people, communities
and businesses along the route, including the creation of local
jobs.
, Chair of the Public Accounts Committee, said
“HS2 is already one of the single most-expensive
taxpayer-funded programmes in the UK but there’s actually no
clear end in sight in terms of the final cost, or even the final
route. The project was plagued by a lack of planning and
transparency from the start and there are many difficulties
ahead.
“This project cannot simply keep sinking more taxpayer funds
without greater clarity on the later phases. The development of
Euston is a real challenge that must be resolved swiftly now.”
, Deputy Chair of the Public Accounts Committee,
said "For the first time, HS2 limited has given us
estimated costs and delivery times for each section of Phase 1.
However, they have given us an estimate of £2.6 billion cost for
the redevelopment of Euston station, which may or may not be
realistic, but they have not given us a date by which Euston will
be integrated into the rest of Phase 1 and indeed this Phase will
initially open at Old Oak Common. If Euston does not come on
stream fairly soon after this the major cost benefits of Phase 1
will be curtailed.
"The overall cost of Phase 1 is £35billion with a £10 billion
contingency, which would appear to be achievable. However, plans
are not yet complete as to how Phase 1 will be integrated into
Phase 2, and the costs of Phase 2a and 2b are far less certain.
Therefore, the total wide estimate of building the entire railway
is far less certain, between £72 to £98 billion, and could well
exceed even that."
PAC report conclusions and
recommendations
-
While it is encouraging that the civil construction
elements of Phase One seem to be on a firmer footing, the scale
of the work that still needs to be done means future costs
remain uncertain.We have previously criticised the
Department and HS2 Ltd’s lack of transparency over the
programme’s delivery timeline and budget, and Government
subsequently committed to six-monthly reporting to Parliament
on the programme. HS2 Ltd is now able to provide us with a
clearer explanation of costs than we have previously seen in
its reporting to Parliament. HS2 Ltd reports that it has spent
£11 billion to date and used £0.4 billion of its contingency,
out of a total budget of £44.6 billion (2019 prices). The
contracting of Phase One civil construction, worth £15.5
billion, is complete, of which £2.5 billion has been spent. HS2
Ltd considers the budget for Phase One to be realistic and
estimates it has completed approximately 20% of the work,
having spent 5% of its contingency. While Phase One appears to
be in a better place than when we reported in 2020, the risk of
cost increases remains. A substantial amount of the Phase One
programme is still to be procured and HS2 Ltd is already
reporting cost pressures of £0.8 billion from activities such
as delayed enabling works and Euston station. HS2 Ltd is yet to
fully quantify the final cost of the impacts from the COVID-19
pandemic but estimates the cost to be between £300 million and
£400 million at the end of 2020. If these costs are validated,
they will be covered by the government-retained contingency of
£4.3 billion.
Recommendation: The Department and HS2 Ltd should set out
as part of its future 6-monthly reporting to Parliament, a more
comprehensive view on risk to the Phase One cost estimate and the
use of contingency. The reporting of costs should be consistent
over time and include, preferably in tabular format, areas such
as:
- how much Phase One contingency has been used/remaining (£)
and the proportion of contingency used/remaining (%). This should
be included for: HS2 Ltd contingency (A); government-retained
contingency (B); and, the total Phase One contingency (A+B);
- details of the cost pressures, including the value (£) of
those that HS2 Ltd has confirmed and accepted, and those that HS2
Ltd is assessing as potential and not yet confirmed;
- a clear indication of whether cost pressures have increased,
decreased or remained stable since the preceding 6-monthly
report; and,
- progress being made on the cost efficiencies programme, with
a supporting narrative.
-
The Department has made little progress on the design
and delivery at Euston since we last reported, and we remain
concerned that time is running out. Euston station is
a key element of the programme both as the London terminus for
High Speed 2 and a link to existing railway network and London
Underground. We raised concerns over the lack of clarity of the
design and delivery of Euston station in our May 2020 report,
but the Department has made no final decisions since then. The
redevelopment of Euston station is currently estimated to cost
£2.6 billion. Despite HS2 Ltd telling us last year that the
design of the station was ready for planning consent, the
Department has spent the past 15 months looking for cost saving
options and efficiency opportunities, including the potential
for a smaller station. HS2 Ltd asserts that it is getting close
to the point where the programme will literally run out of time
if a decision is not made soon, and that Old Oak Common is
being set as the London terminus when the railway first opens
to decouple it from the risks at Euston. The Department
recognises that Euston is a very urgent and immediate challenge
and expects to report on progress in autumn 2021. We recognise
the benefits Euston provides, such as redevelopment
opportunities around the station, as well as its complexity in
being built at a busy operational railway in a city centre
location, but the uncertainty of this part of the programme is
substantial. This impacts businesses, passengers, residents and
other industry stakeholders. This uncertainty needs to be
resolved urgently, and the Department needs to ensure
appropriate assurance has been completed on the decisions taken
on the design and delivery arrangements.
Recommendation: The Department should set out in its next
6-monthly report to Parliament:
- the decisions that it has made about Euston;
- details of the assurances it has undertaken;
- its timeline on when remaining decision points will be met;
and,
- any impact on the Euston opening range of 2031 to 2036.
-
HS2 Ltd has started planning how it will integrate its
systems for Phase One to ensure the railway works, but this is
an inherently risky part of the programme. We
previously raised concerns that, given the scale of the
programme and its future impact on the rail network, if the
Department does not give enough attention to managing the
interdependencies within HS2 and other rail programmes,
passengers and services would suffer. In addition to the
stations and infrastructure, HS2 needs to ensure that railway
systems can work together in order for services to run. HS2 Ltd
is attempting to avoid the Crossrail experience of failing to
integrate the various systems required to operate the railway.
HS2 Ltd is starting to plan its approach to integration of
systems early and has proposed a delivery approach which would
incentivise alliances between contractors. HS2 Ltd recognises
that this approach is bold and complex and has not been
undertaken in the railways before, although there are examples
in the oil and gas sector. The systems required to operate the
railway in Phase One will not be installed and tested until the
late 2020’s. However, procurements on the parts of the
programme that are integral to the successful integration and
operation of the railway are underway. Smaller contracts, such
as tunnel safety doors, have already been procured, and larger
contracts, such as track, electrification and signalling, are
expected to be procured over the next two years.
Recommendation: HS2 Ltd must continue to monitor and
report on both progress and the time allocated to systems
integration as part of the regular 6-monthly updates to
Parliament, and inform the Committee promptly if the time
allocated to these latter stages is at risk of being squeezed.
When it has announced the winner of its competition for the
rolling stock contract, HS2 Ltd should write to the Committee to
explain how the design and delivery of the train will support the
integration of the systems required to operate the railway.
-
We are increasingly concerned that the Department and
HS2 Ltd do not yet know how they will turn the benefits
promised from High Speed 2 into a reality, including what
additional investments will be needed or how these will be
funded.The Department claims that High Speed 2 is a
catalyst for investment, jobs and growth but also acknowledges
that it needs to focus on making sure that the programme
achieves what is intended. The Department needs to turn those
intentions into a plan that brings together local authorities,
the private sector and other Departments. There are some
examples of the Department encouraging private sector
investment, such as £50 million announced in the Budget for
development around the Birmingham Interchange station, and the
programme’s promise of regional job creation. However, despite
hearing that pockets of activity to realise benefits is
happening, we are concerned the Department does not yet have an
integrated programme to delivering these benefits. We are
disappointed to hear that local jobs are not being created in
the numbers expected. Realising the benefits for the Midlands
and the North is dependent on removing the uncertainty around
the outcome of the integrated rail plan.
Recommendation: The Department and HS2 Ltd should write to
the Committee within three months, describing their strategy to
identify, monitor and evaluate the benefits of the programme. The
Committee will monitor what progress has been made against this
when we next revisit High Speed 2.
-
The Department and HS2 Ltd are not adequately engaging
with the Department for Education to secure the skills required
for the future of the programme and training the next
generation of skilled workers. We have repeatedly
raised concerns that the Department and HS2 Ltd did not have
the skills or capability they needed now or in the future to
successfully deliver the programme. The Department and HS2 Ltd
have repeatedly failed to convince us that their plans to
secure the future skills and capability needed are enough. In
2016, HS2 Ltd and the Department told the previous Committee
that the National College for High Speed Rail would be crucial
in training people in the skills required for High Speed 2 and
other infrastructure projects. The college has since become the
National College for Advanced Transport & Infrastructure
and, most recently, merged with the University of Birmingham.
The Department admits that the performance of the college has
been disappointing and hopes that its latest merger, new
leadership and new curriculum from September 2021 will be an
opportunity to get the best out of the arrangement. Yet the
Department’s involvement with the college has been limited as
it falls under the Department for Education’s accountability
remit. We are disappointed in this lack of engagement, as it is
in the Department’s strategic interests to have a strong
relationship with the college and ensure it provides the skills
and curriculum High Speed 2 and other infrastructure projects
need.
Recommendation: The Department must proactively engage
with the Department for Education and other relevant education
providers to ensure there are plans in place for further
education colleges to get the through-flow required for the
programme. The Department should write to us to explain how it is
engaging with these stakeholders within three months.
-
We are already concerned about the volume of complaints
on disruption from the programme which does not bode well for
the future as more communities will be impacted as construction
progresses. HS2 Ltd estimates it has handled 124,000
queries over the past three years and interacted with over
76,000 people along the route. It is engaging with the supply
chain, its contractors and local MPs to help inform communities
about its work. However, the number of complaints from the
public about High Speed 2 has increased as main construction on
Phase One has started. Complaints to the Independent
Construction Commissioner HS2 rose to 86 in the first quarter
of 2021 from 74 in the previous quarter. The majority of
complaints are about the impact of construction on roads and
traffic, vegetation clearance and about noise and vibration.
Due to the scale of the programme and the time until the
railway is complete, complaints are likely to increase as the
programme progresses. It will be critical for HS2 Ltd to
develop a way of embedding the lessons it has learned into its
day-to-day processes, so that mistakes from Phase One are not
repeated in Phase Two, and that community engagement and
environmental concerns are more proactively addressed by the
company.
Recommendation: The Department and HS2 Ltd should write to
the Committee within three months setting out how they intend to
resolve the issues around community engagement and the
environment observed by the Committee in this report.