: This statement
concerns the development consent order (DCO) application for the M25
Junction 10 / A3 Wisley Interchange improvement made by Highways
England under the Planning Act 2008,which had been submitted to the
Planning Inspectorate on 19 June 2019.
Under section 98(1) of the act the examining authority appointed
to examine the application must complete its examination within 6
months. Under section 98(4) the examining authority must submit
its recommendation report to the Secretary of State within 3
months of its completion of the examination. Under section 107(1)
of the act, following receipt of the examining authority’s
recommendation report, the Secretary of State must decide whether
to grant development consent within 3 months.
Sections 98(4) and 107(3) of the act give the relevant Secretary
of State power to set new deadlines in respect of the above which
are later than the statutory maxima. For this application, the
relevant Secretary of State is the Secretary of State for
Transport. In exercising this power,the Secretary of State for
Transport must, amongst other things, make a statement to
Parliament announcing the new deadlines.
The examination for the M25 Junction 10 DCO began on 12 November
2019 and is due to close on 12 May 2020. The recommendation
report would need to be sent to the Secretary of State on or
before 12 August 2020. A decision in this case would therefore be
made on or before 12 November 2020.
The deadline for the completion of the examination is to be
extended to 12 July 2020 (an extension of 2 months) to enable
examination hearings postponed in the light of government advice
concerning coronavirus (COVID-19) to be rescheduled and held in a
virtual forum. Consequently, the deadline for the examining
authority to submit its recommendation report to the Secretary of
State for Transport is amended to 12 October 2020 and the
deadline for the Secretary of State for Transport to take his
decision is amended to 12 January 2021.
The decision to extend the examination under the Planning Act
2008 regime is not taken lightly and reflects the exceptional
public health circumstances the country finds itself in.
The decision to set new deadlines is without prejudice to the
decision on whether to grant development consent.