The two PFI (Private Finance Initiative) hospitals that Carillion
was building at the time it collapsed - Royal Liverpool University
Hospital and Midland Metropolitan Hospital - are currently due
for completion several years late.1
However, the government has ensured that most of the
increased construction costs so far have been borne by the
private PFI investors and Carillion, rather than the taxpayer,
according to a new investigation by the National Audit Office
(NAO), published today.
The NAO’s report finds that the 646-bed Royal Liverpool,
which was due to open in June 2017, is now forecast to be
completed more than five years late, in the autumn of 2022, and
the Liverpool University Hospitals NHS Foundation Trust has not
yet set an opening date. It is now predicted to cost a total of
£1,063 million to build and run compared to the original £746
million.2 The taxpayer is
currently expected to pay £739 million of this, a reduction of 1%
from what was originally planned.
The 669-bed Midland Metropolitan, which was originally due
to open in October 2018, is now expected to open in July
2022. The hospital is due to cost at least £988
million in total to build and run - over £300 million more than
the original £686
million.3 The
taxpayer is currently expected to pay £709
million of this, an increase of 3% from what was originally
planned.
The private sector has borne most of the cost increase:
shareholders, investors, insurers and Carillion have lost at
least £603 million on the construction of both projects. The
government wanted to ensure the private sector honoured its
contracts and rejected proposals that it should provide more
public funding to ‘bail out’ the PFI schemes or reduce the risk
that lenders were exposed to.
There were significant construction problems and delays
before Carillion went into liquidation on 15 January 2018 but the
contractor’s collapse created more delay. Work on both sites
stopped while the hospital Trusts, government and the private
investors attempted to rescue the projects. By September 2018,
these attempts had failed; government decided to terminate the
PFI schemes and provide public financing to complete the
hospitals. It has then taken time to put in place new contracts
and restart the projects.
The full extent of construction problems at Royal Liverpool
began to emerge after Carillion collapsed and over the course of
2018. The new construction contractor has had to strip out three
floors of the building and start major work to reinforce the
structure with steelwork and additional reinforced
concrete.
The Department of Health & Social Care (DHSC) paid £42
million compensation to Royal Liverpool’s investors to terminate
the PFI contract. The contract required the Trust to pay
compensation to the PFI company’s lenders, based largely on the
estimated cost to complete the hospital, before the actual cost
to complete the hospital was known. Had the Department and Trust
better understood the cost to complete the hospital, they may not
have paid anything to the lenders. The estimated cost of
completing the hospital has risen from £117 million in September
2018, when DHSC agreed the termination payment, to £293 million
now.4
The new suppliers for both the Trusts were chosen without
competition. After the termination of the PFI contract, in order
to restart the Liverpool project without further delay, the
Liverpool Trust agreed contracts with several new suppliers
without a public procurement process. The Sandwell and West
Birmingham Hospitals NHS Trust ran a public procurement for the
contract to complete Midland Metropolitan taking 15 months, which
only attracted one viable bidder.
There are significant risks of further delays and added
costs at the hospitals, although their situations are different.
Both Trusts are now directly managing the contracts with new
construction firms. At Midland Metropolitan, the Sandwell Trust
has negotiated a ‘target price’ for work by its new contractor,
Balfour Beatty, and prices should not rise unless the Trust
changes the scope of the project or there are unforeseen problems
with Carillion’s work. At Royal Liverpool, the new main
contractor, Laing O’Rourke, has no contractual incentives to
control costs. NHS England and NHS Improvement has worked with
the Liverpool Trust to develop additional oversight arrangements
such as using an independent construction consultancy to advise
on the appropriateness of costs.
- ENDS -
Notes for
Editors
-
The delay at Midland Metropolitan Hospital is 3 years and
9 months, and at Royal Liverpool University Hospital more than
5 years.
-
This includes £293 million for remedial work to the
structure and to complete construction.
-
This includes £315 million still to be spent to complete
the construction.
-
Under the calculation used for the compensation payment
for the termination, the cost to complete is deducted from the
amount due, so a rise to £293 million means no compensation
would be paid.