E.ON: Offshore wind project Rampion starts power generation
Tuesday, 28 November 2017 12:09
The offshore wind farm Rampion in the English Channel has started
generating electricity. According to E.ON, the first turbine was
commissioned. 115 additional turbines will be connected to the grid
in stages over the next few months. The offshore work for the
Rampion project began in autumn 2015 with the preparation of the
seabed for the turbine foundations. The first monopile was
installed at the beginning of 2016. The installation of the
turbines began in March 2017 and was...Request free trial
|