The National Audit Office has today published the findings from
its investigation into equipment cannibalisation in the Royal
Navy.
The Royal Navy operates ships, submarines and helicopters, which
comprise complex systems made up of thousands of parts, to meet
the United Kingdom’s defence requirements. The Navy needs
additional parts to maintain and repair its equipment. When
vessels require parts that are unavailable and no other solution
is available, the Ministry of Defence (the Ministry) can
authorise that they are taken from other equipment – a process
known as equipment cannibalisation.
The key findings of the investigation are:
- · Equipment
cannibalisation can be necessary but should only happen when no
other solution is available. The Ministry guidance states
“cannibalisation will only be conducted where no other solution
is available.” Decision-makers consider operational priorities
and the estimated time to obtain new parts. In the last five
years, between 0.3% and 1.4% of parts provided to the main
classes of ships and submarines have been cannibalised parts.
However, each instance has a wider impact beyond the part being
replaced and can signify broader issues with the process for
getting spare parts.
- · Across ships
and submarines, equipment cannibalisation has increased 49% in
the last five years, with a total of 3,230 instances involving
6,378 parts. During 2016-17, there were 795 instances of
equipment cannibalisation. This equates to 66 instances a month,
compared to 30 a month in 2005. Since 2004, the Navy has reduced
its fleet of ships and submarines by 31% from 127 to 87, meaning
that a higher proportion needs to be deployed, or ready to
deploy, at any one time in order to meet defence requirements. In
2016-17, ship and submarine equipment cannibalisation accounted
for 60% of instances across the Navy. Navy Merlin helicopters
make up the remaining 40%.
- · Some 40% of
ships and submarines receiving cannibalised parts needed them so
they could be ready for operations or training. In these
cases, equipment cannibalisation rectified issues that would have
reduced the operational capability of ships and submarines. The
remaining 60% of ships and submarines did not need the parts for
operations or training. For example, in some cases the parts were
required to complete planned maintenance work to a specified
schedule so as to avoid potential delays and additional costs.
- · Our analysis
shows 71% of parts cannibalised on the basis of operational need
were low value, but the cost of moving the parts could be much
greater. The majority of cannibalised parts cost less than
£5,000, with less than 1% valued at over £500,000. The Ministry
does not know how often the cost of replacing cannibalised parts
exceeds the value of the part being replaced. The Ministry’s
analysis, covering 146 Type 23 equipment cannibalisations in
2012, showed that in 50% of these cases, the cost of equipment
cannibalisation was equal to, or greater than, the value of the
part. In 25% of cases it was four times greater. Even though
equipment cannibalisation has increased, the Ministry has not
updated or broadened its analysis.
- · The need for
equipment cannibalisation is exacerbated by both a lack of
information about when parts will be delivered, and delays in
receiving parts on time. In March 2017, the DE&S Ships
Operating Centre met 55% of part demands from ship and submarine
crews by the required date (target 75%). The Submarine Operating
Centre met 63% of demands (target 80%). At the same time, of
17,038 ship part demands already past their required delivery
date, 34% had no recorded forecast delivery date. Identifying a
forecast delivery date can be more difficult where the Ministry
has contracted-out support arrangements. The Ministry has
undertaken a number of initiatives to improve ship and submarine
supply chain management.
- · The Ministry
does not routinely monitor the use, causes and impact of
equipment cannibalisation across the Navy. The Ministry
considers and assesses equipment cannibalisation and trends over
time for individual vessel types. There is no overall
accountability for managing equipment cannibalisation across the
Navy or routine data collection or analysis assessing why
equipment cannibalisation occurs or its impact. This information
gap makes it difficult to determine when equipment
cannibalisation is becoming more routine, its underlying causes,
and the trade-offs between cost savings and equipment
cannibalisation.
- · The Ministry
has taken decisions to reduce support without complete
information to fully assess and manage the impacts and costs. To
remain within its budget, the Navy reduced its maritime support
budget by 6% (£271 million) in-year in the last two years. Of
these reductions, an estimated £92 million could increase the
need to cannibalise parts. In particular, the Ministry decided
not to invest in complete technical documentation or in fully
cataloguing parts when vessels were brought into service.
- · Each
instance of equipment cannibalisation can delay programmes,
create additional engineering risks and add to the work of staff,
affecting morale. Equipment cannibalisation has a number
of impacts the Ministry needs to manage including:
a) Programme
delays: In the last five years, the number of equipment
cannibalisations from the Astute-class submarine production line
increased 43%, from 77 instances in 2012-13 to 110 in
2016-17. Cannibalisation caused a 42-day delay and the
Ministry having to pay an additional £4.9 million for the third
Astute submarine and has also affected other boats.
b) Engineering
risk: Cannibalised parts, along with additional
parts that must be removed to gain access to them, may be damaged
whilst being removed, transported or re-installed. An estimated
11% of the parts recorded by ships as having shortcomings in
their material, design or documentation were cannibalised.
c) People: The
2017 Navy risk register identified a lack of spare parts as a
risk to operational capability given its demoralising effect on
personnel.
Key facts
|
|
3,230
instances of ship and submarine cannibalisation, April
2012 to March 2017
|
49%
increase in equipment cannibalisation, April 2012 to
March 2017
|
0.3%-1.4%
percentage of all parts provided by DE&S that were
cannibalised across main ship and submarine types,
April 2012 to March 2017
|
|
26%
|
instances where the same part was cannibalised three or
more times
|
|
71%
|
percentage of cannibalised parts valued at less than
£5,000, April 2012 to March 2017
|
|
59
|
Average number of equipment cannibalisations per
Astute-class submarine in 2016-17
|
|
£92 million
|
Estimated maritime support funding removed in-year from
2015-16 and 2016-17 budgets that could increase the need
to cannibalise parts
|
|
34%
|
Part demands past their required delivery date with no
forecast due date for their receipt
|
|
21%
|
Shortfall in trained and qualified staff within DE&S
navy supply teams
|
|
5%
|
Percentage of part demands where parts identified as
obsolete
|
Notes for Editors
- 1. In some circumstances,
equipment cannibalisation can be the most effective way to keep
vessels’ operational or maintenance schedules on track, for
example, during periods of high intensity operations. However, it
can also be costly and disruptive and can divert resources from
other activities.