The Department for Infrastructure has provided an update on the
position with over 300 landowners whose land is being vested as
part of the first phase of construction of the A5 Western
Transport Corridor (Section 2 and Section 3 Phase 1B).
The Department recognises the uncertainty that landowners, their
families and businesses affected by the A5 Western Transport
Corridor have faced over a prolonged period.
Since the High Court judgment in June 2025, officials have
continued an extensive programme of engagement with landowners.
Every affected landowner has been offered the opportunity to meet
individually with the project team, while officials have
maintained regular contact through direct correspondence and
engagement with landowners and their appointed professional
agents.
The Department also meets regularly with the Ulster Farmers'
Union, including at senior official level, and this engagement
has continued following the recent Court of Appeal proceedings.
The legal proceedings and the quashing of the Vesting Orders
disrupted the normal compensation process and delayed access to
compensation funding for some affected landowners. Any claims
arising from evidenced financial impacts will be assessed
independently by Land & Property Services on a case-by-case
basis in accordance with the statutory compensation framework.
The Minister has given a commitment that major construction work
will not commence on any lands until after 31 December 2026. Any
necessary activities before that date remain limited to surveys
and other essential preparatory work.
The Department recognises the important role professional agents
play in supporting landowners and meets reasonable professional
fees associated with that representation.
While the Department awaits the formal order giving effect to the
Court of Appeal judgment of 6 October 2026, officials will
continue to engage and update affected landowners as the position
develops.
A Questions and Answers section of the website has been
created to help landowners understand the current position
is available at https://www.infrastructure-ni.gov.uk/articles/a5wtc-website-updates-following-court-appeal-judgement
It will be updated as further information becomes available.
Notes to editors:
- The A5 Western Transport Corridor (A5WTC) is an NI Executive
led scheme which will provide 85 kilometres of new road of which
82km would be dual carriageway, from New Buildings to the border
at Aughnacloy. It will improve links between the urban centres in
Strabane, Newtownstewart, Omagh, Ballygawley and Aughnacloy and
provide a strategic link with international gateways.
- The A5WTC is currently split into three Sections, Section 1
New Buildings to South of Strabane, the Authorised Section South
of Strabane to Ballygawley (Section 2 and Section 3 Phase 1B) and
Section 3 Phase 3 Ballygawley to the border south of
Aughnacloy. Contractors have been appointed for the
delivery of each.
- Scheme objectives are to help tackle regional imbalance,
improving the economy, job prospects and prosperity, better
connecting communities, but most importantly the A5WTC is about
saving lives.
- The A5WTC has a long and protracted history, facing many
challenges including three public inquiries and four legal
challenges. These challenges have led to significant
pressure on costs and programme.