Lord Rosser (Lab): Work on the Great
Western electrification commenced in June 2010 and was due to
be completed in 2016-17, but was not completed until 2019-20. The
project ran into major difficulties, causing repeated extensions to
deadlines and costs to increase by more than 300%, to around £2.8
billion in 2018 from £874 million in 2013. Despite this dramatic
increase in costs, the project still had to be scaled back to keep
cost increases merely in excess of...Request free trial
|